Analisis Faktor-faktor Perubahan Design Terhadap Proyek Konstruksi Pelebaran Jalan Tol Jakarta-Merak (Area Cikupa)
DOI:
https://doi.org/10.21512/emacsjournal.v2i3.6561Keywords:
Toll Road, Construction, Project Delay, Design Changes, SPSSAbstract
In every project, job changes are always happening and almost unavoidable. One of the factors that influence job change is a design change. This study analyzes the design changes that have caused delays in the Jakarta-Merak toll road widening project in the Cikupa area—collecting data using literature studies and questionnaires with five Linkert scales. The analysis used SPSS version 22. The research finding is five variables of design changes and changes due to the land’s location to be used as a project, which are the leading causes of changes in this project’s design.
Plum Analytics
References
Boon, J., Yap, H., Tunku, U., Rahman, A., Abdul-rahman, H., & Wang, C. (2015). Impacts Of Design Changes on Construction Project Performance : Insights From A Literature Review, (November).
George Lois (2018). Analisis Faktor yang Berpengaruh Terhadap Keterlambatan Proyek Pelebaran Jalan Tol Tangerang-Merak & Simpang Susun Cikupa Paket 2
Indonesia, U., Ariefasa, R., Teknik, F., Studi, P., Sipil, T., & Konstruksi, K. M. (2012).
Kasus, S., Jalan, P., & Trans, T. O. L. (2016). Analisis Risiko Keterlambatan Waktu Pada Proyek Pembangunan Jalan Tol Trans Sumatra. University lampung.
Khahro, S. H., Ali, T. H., & Akhund, M. A. (2017). Effect Of Change Orders On Project, (January 2018).
Kristiana, R. (2017). Identifikasi Penyebab Risiko Keterlambatan Proyek Konstruksi Bangunan Gedung Tinggi Hunuian ( Studi Kasus : Proyek Pembangunan Condotel Dan Apartemen Bhuvana Resort Ciawi , Bogor ).
Love,P.E.D. et al., 2002. Using system dynamic to better understand change and rework in contruction project management system. International of Project Management, 20 (6), pp.425-436
Najah, A., Pontan, D., Studi, P., Sipil, T., Metode, M., Deskriptif, S.Daerah, P. (2018).Identifikasi Peringkat Faktor penyebab Keterlambatan, 133–140.
Pmbok 5th edition, 2016
Sulaiman, M. (2017). Analisis penyebab keterlambatan pelaksanaan proyek ditinjau dari waktu pelaksanaan di provinsi aceh 1), 1, 405–418.
Downloads
Published
Issue
Section
License
Authors who publish with this journal agree to the following terms:
a. Authors retain copyright and grant the journal right of first publication with the work simultaneously licensed under a Creative Commons Attribution License - Share Alike that allows others to share the work with an acknowledgment of the work's authorship and initial publication in this journal.
b. Authors are able to enter into separate, additional contractual arrangements for the non-exclusive distribution of the journal's published version of the work (e.g., post it to an institutional repository or publish it in a book), with an acknowledgment of its initial publication in this journal.
c. Authors are permitted and encouraged to post their work online (e.g., in institutional repositories or on their website) prior to and during the submission process, as it can lead to productive exchanges, as well as earlier and greater citation of published work.
USER RIGHTS
All articles published Open Access will be immediately and permanently free for everyone to read and download. We are continuously working with our author communities to select the best choice of license options, currently being defined for this journal as follows: Creative Commons Attribution-Share Alike (CC BY-SA)